Harvest Ridge Wind Farm Construction Updates

Please note dates are planned and may change. Changes will be reflected in the next day update.

If you have any questions or comments, please contact the following:

Email: harvest.ridge@edpr.com      Phone: 800-970-6841

THIS WEEK: June 29 - July 5

All Activities Are Weather Dependent

Escorted Heavy Hauls have the right of way

Please be careful driving on site and stay off the shoulders.

  • Continued deliveries and offloads
  • Civil restoration on south side of site
  • Road grading and maintenance ongoing
  • Awareness of road washout repairs and cleanup throughout project site due to heavy flooding

 

2-Day Look ahead

***NOTE: Crane Road Crossing/Road Closure*

  • Complete

Civil Work

  • Road Maintenance –  Dust Control
  • Site Road Radii Removal – 1450 & 2350
  • Beauty Ring – 51, 15 Series, 34-38
  • Subsoil Removal – 15 Series, 35-37
  • Site Restoration – Substation
  • Public road maintenance
    • Ongoing dust control support on CR 2450 (very dusty this a.m.), T09 access road, T06 access
      roads
    • Dust control on all site roads as necessary

Tower Installation

  • Complete

Component Deliveries

  • Complete

Next Week: July 6- July 11

  • Cranes movements, road crossings
  • Site restoration with heavy equipment and trucks
  • Equipment breakdown, cranes,  to make ready for transport

 