Harvest Ridge Wind Farm Construction Updates

Please note dates are planned and may change. Changes will be reflected in the next day update.

If you have any questions or comments, please contact the following:

Email: harvest.ridge@edpr.com      Phone: 800-970-6841

THIS WEEK: May 31 - June 6

All Activities Are Weather Dependent

Escorted Heavy Hauls have the right of way

Please be careful driving on site and stay off the shoulders.

  • Continued deliveries and offloads
  • Civil restoration on south side of site
  • Road grading and maintenance ongoing

 

2-Day Look ahead

***NOTE: Crane Road Crossing/Road Closure***

  • Thursday, June 4: Crossing 2750E 18 to 16 (~10:30)

Civil Work

  • Access Road , Crane Pad Work – T2, T3, T15D
  • Proof Rolls/Test Rolls – T18
  • Public road maintenance
    • Grading
    • Dust control on all site roads as necessary

Tower Installation

  • T03 – Mid 1, Mid 2
  • T12 – Mid 3, Top, Nachelle, Blades
  • T19 – Tower Top, Nacelle Blades
  • T13 – Blades

Component Deliveries

  • Complete

Next Week: June 7 - June 13

  • Cranes movements, road crossings
  • Site restoration with heavy equipment and trucks