Harvest Ridge Wind Farm Construction Updates

Please note dates are planned and may change. Changes will be reflected in the next day update.

If you have any questions or comments, please contact the following:

Email: harvestridge@edpr.com      Phone: 800-970-6841

THIS WEEK: July 14 - July 20

  • Establish laydown yard for construction trailers.
  • Continuing public road improvement work on 2350 E and 2450 E moving north from Highway 3 to 1350N.
  • Public road improvement work on 1250N.
  • Installing access road entrances and laybys on public roads.

2-Day Look ahead

  • Aggregate cap being laid on 2350 E between 1150 N and 1250 N.
  • Initial pulverization of 1250 N between 2350 E and 2450 E.
  • Installing access road entrances and laybys on 2450 E between 1250 N and 1350 N.

Next Week: July 21 - July 27

  • Continuing public road improvement work on 2350 E and 2450 E moving north to County Highway 4.
  • Installing temporary power to laydown yard site.
  • Mobilizing construction trailers to laydown yard site.