THIS WEEK: March 29 - April 4

Date: April 1, 2020

All Activities Are Weather Dependent

Escorted Heavy Hauls have the right of way

Please be careful driving on site and stay off the shoulders.

Progress Planned Today:

Towers Installation:

T51-Base, Mid1, Mid2

T42-Mid3, Mid4, Top Tower, Nacelle, Blades

T57-Mid3, Top Tower, Nacelle, Blades

T09-Hub

Deliveries:

T34-Base

T51-Mid1, Mid2, Mid3, Top Tower, Nacelle, Hub

T09-Drive Train, Hub

T55-Blades

Any Obstructions or Changes:

**3rd Main crane will be arriving April 3rd and set up at T51 please be cautious.

Caution: Gravel Truck Route

  • Traveling North on 2450 cross 1250 South 2350
  • Gravel to Substation

Caution:

  • Crews working near public right of way at multiple locations.

Continued:

  • Site civil and steel work at substation.  Expect equipment and hauling traffic.

 

2-Day Look ahead

All Activities Are Weather Dependent

Escorted Heavy Hauls have the right of way

Caution: Gravel Truck Route

  • Traveling North on 2450 cross 1250 South 2350

Caution:

  • Crews working near public right of way at multiple locations.

Continued:

  • Site civil and steel work at substation.  Expect equipment and hauling traffic.

Next Week: April 5 - April 11

 

  • Equipment Deliveries
  • Continued culvert replacement and installation work.
  • Construction equipment traffic on roadways and working near roadways.
  • Trenching activities between turbines