THIS WEEK: September 8 - September 14

  • Continued earth work and equipment installation at laydown yard.
  • Continued access road entrance and layby installation.
  • Continued site civil work at substation.  Expect equipment and hauling traffic.
  • Boring crews working near roadway.
    • 2350/1250
  • Road Closures 9/9
    • Hwy 36 to 1350 and Back for Ditch Work
    • Hwy 5 to 2730
  • Turn Radius
    • 2450/1450
    • 2350/1350

2-Day Look ahead

  • Shoulder work/ grading on 2350 E between 1350 N and Highway 36.  Rolling road closures.
  • Road work on 1350 N between Highway 5 and 2730 E, road will be closed over night.
  • Grading work ongoing on 2750 E between 1550 N and 1425 N, road closed.
  • Boring crews working near roadway on 2750 E and 2730 E, please use caution.

Next Week: September 15 - September 21

  • Initial site work on private access roads and entrances.
  • Continued culvert replacement and installation work.
  • Earth work and mobilization at substation site.
  • Construction equipment traffic on roadways and working near roadways.
  • Boring crews working near roadways.